Odisha Tribunal Cancels OSHB’s Rs 21-Lakh Flat Price Hike, Orders 10.15 pc Interest

Bhubaneswar, Nov 21: In a significant ruling in favour of a homebuyer, the Odisha Real Estate Appellate Tribunal (OREAT) has set aside an unexplained price escalation of nearly ₹21 lakh imposed by the Odisha State Housing Board (OSHB) on a four-bedroom deluxe flat at Kharavela Enclave in Jagamara, Bhubaneswar. The tribunal has also directed the Board to pay interest at 10.15 per cent per annum for the delay in handing over possession.

Odisha Tribunal Cancels OSHB's Rs 21-Lakh Flat Price Hike, Orders 10.15 pc Interest

 Representational Image 

The dispute centres on a flat whose price was initially fixed at around ₹67 lakh but was subsequently increased to approximately ₹88 lakh by the Housing Board. Finding no satisfactory justification for such a steep revision, the tribunal held that the additional financial burden imposed on the allottee was arbitrary and could not be sustained.

The order also addresses the prolonged delay in delivering the property, directing OSHB to calculate interest from June 13, 2017 — the scheduled date of possession — until the actual handover of the flat.

Tribunal Questions Unexplained Escalation in Flat Cost

The homebuyer had challenged the Housing Board’s decision to raise the price substantially without providing a convincing explanation for the additional amount.

After examining the matter, OREAT rejected the revised pricing, observing that a housing authority could not unilaterally increase the cost of an allotted property from around ₹67 lakh to ₹88 lakh without establishing valid grounds for the escalation.

The tribunal’s intervention effectively removes the disputed increase of nearly ₹21 lakh, providing considerable financial relief to the allottee.

Kharavela Enclave Project Dates Back to 2011

The dispute has its roots in the Kharavela Enclave housing project, launched by OSHB in 2011. The buyer received a provisional allotment letter in June 2014 and had paid ₹14.73 lakh towards the flat.

The project was registered under the Real Estate (Regulation and Development) Act in September 2018.

In examining the applicability of RERA, the tribunal noted that construction had not been completed when the legislation came into force in 2016. The project, therefore, fell within the ambit of the Act.

The case has once again brought attention to the responsibilities of housing authorities towards allottees, particularly regarding timely possession, transparent pricing and accountability for construction delays.

OSHB Cannot Blame Encroachment for Possession Delay

One of the important issues examined by the tribunal was the Housing Board’s argument that encroachment on the project land had contributed to the delay in construction and possession.

OSHB had sought to present the encroachment as a circumstance beyond its control. However, OREAT rejected this justification, observing that the Board was already aware of the encroachment before inviting applications and collecting money from prospective homebuyers.

The tribunal’s reasoning was that a condition known to the authority before accepting applications could not subsequently be treated as an unforeseen obstacle to escape responsibility for the delay.

The finding is particularly significant because it places responsibility on the housing agency to account for known project-related difficulties before offering properties to buyers.

10.15% Annual Interest from Scheduled Possession Date

Apart from setting aside the disputed price revision, OREAT addressed the compensation payable for the delayed delivery of the flat.

The tribunal modified an earlier direction issued by the RERA authority in June 2019 and ordered OSHB to pay interest at 10.15 per cent per annum.

The interest is to be calculated from June 13, 2017, the original scheduled date for handing over possession, until the date on which the flat is actually handed over.

The direction offers financial relief to the homebuyer for the extended wait and reinforces the importance of adhering to possession timelines in housing projects.

Airport Height Restrictions Also Affected the Project

Kharavela Enclave had previously come under scrutiny over objections raised by airport authorities concerning construction beyond prescribed height restrictions. The issue reportedly contributed to the project’s prolonged delays.

The development has now returned to the spotlight following the appellate tribunal’s decision on the pricing dispute and delayed possession.

For the affected allottee, the ruling addresses two major concerns: the substantial increase in the originally quoted flat price and the failure to deliver possession within the promised timeframe.

The decision also sends a wider message to public housing agencies that unexplained cost escalations and delays cannot be imposed on homebuyers without accountability. For buyers dealing with long-delayed housing projects, the order underlines the importance of transparent pricing, clearly defined possession commitments and the protections available under real estate regulatory law.